The flush-mounted technical installations are completed, we go with the plaster to the ground floor. Installation of facade windows and blinds is completed. Sectional doors and exterior doors fitted. This week, we are starting the horizontal insulation of the floor and completing the installation of the central vacuum cleaner. Outside, the area has been carved for paving stones, we have arranged a lightning protection – rim, distribution channels for cabling and drainage of water from gutters. We can’t wait for the pavers to start working. Despite some minor problems, we stick to the assumed action plan!