Construction progress – 8 Aug.

Inside: electricians finished equipping and wiring switchboards in the brick part, they made cable routes in the hall, distributed power supply and made lighting for the workshop and storage part; the stonemason made a staircase; finishing works on the first floor moved to the stage of filling the walls; the assembly of the mezzanine began in the hall today; the installation of mechanical ventilation and heating in the hall is being completed.
Outside: the distribution of the lightning protection earth electrode has been completed, power cables for external lamps have been distributed, the so-called “sparrows” around the entire facade.