Construction progress – 9 Sep.

Inside: the installation of internal doors has been completed, electricians have started installing lamps, mechanical ventilation and air conditioning are at the final stage, first devices appear in the server room, the floor is already tiled, some rooms are painted; a mezzanine is installed in the hall and a lighting installation has been made.
Outside: external lighting has been installed, rubble has been removed, and a heat pump has been installed.

Construction progress – 8 Aug.

Inside: electricians finished equipping and wiring switchboards in the brick part, they made cable routes in the hall, distributed power supply and made lighting for the workshop and storage part; the stonemason made a staircase; finishing works on the first floor moved to the stage of filling the walls; the assembly of the mezzanine began in the hall today; the installation of mechanical ventilation and heating in the hall is being completed.
Outside: the distribution of the lightning protection earth electrode has been completed, power cables for external lamps have been distributed, the so-called “sparrows” around the entire facade.

Construction progress – 30 Jul.

Inside: the floors have been finished; the engine room has started the process of technical equipment, the air handling unit has been installed, the contractor continues to distribute the ducts; the wall between the hall and the brick building was plastered; internal window sills are embedded; the assembly of the joinery has started; electricians have started work on smaller switching stations.
Exterior: façade works completed; the distribution of rainwater drainage is completed.

Construction progress – 10 Jul.

Inside: internal plasters finished, underfloor heating pipes laid, mechanical ventilation ducts in progress, main electrical switchboard installed, passages through the fire wall secured, we are finishing insulation of the wall between the hall and the brick building, this morning the end flooring team came in.
Outside: the façade is 80% made, the paving stones are finished.

Construction progress – 5 May

Inside: horizontal insulation of the first floor is completed, fire gates have been installed, this week we plan to finish internal plastering.
Outside: we have started thermal insulation of the office building and paving works.

Construction progress – 26 Apr

The flush-mounted technical installations are completed, we go with the plaster to the ground floor. Installation of facade windows and blinds is completed. Sectional doors and exterior doors fitted. This week, we are starting the horizontal insulation of the floor and completing the installation of the central vacuum cleaner. Outside, the area has been carved for paving stones, we have arranged a lightning protection – rim, distribution channels for cabling and drainage of water from gutters. We can’t wait for the pavers to start working. Despite some minor problems, we stick to the assumed action plan!

Construction progress – 7 Apr

Electrical installation of the floor is being completed, water installation and sewage system as well -> today we start plastering the floor, our first new electronics workshop, which will extend the expansion of services for regeneration of drivers for high-speed gates [ www.naprawa-sterownikow.com.pl ]

Construction progress – 9 Mar

Looking at the sky and the traffic on our site, it can be said that TODAY is the spring solstice. A lot is happening. In total, today several dozen people are working on the construction of our headquarters. The assembly company is slowly finishing installing normal windows, there will remain to be facades to be made. The team of the General Contractor dug the septic tank in the morning, now it is insulating the roof of the office building. The air-conditioning company installs the condensate drains. And in the large hall, horizontal insulation was made in the morning and pears with concrete begin to slide down – we pour the final industrial floor.

Construction progress – 2 Feb

Flooded roof. We are finishing building partition walls on the ground floor. The hall at the stage of finishing works – planks, gutters, etc.

Construction progress – 18 Jan

The load-bearing walls of the brick building are finished. Tomorrow the ceilings arrive on the roof. Today, we install roof panels in the hall. We are rapidly approaching the open shell.