Construction progress – 25 Nov.

Inside: the balustrades on the staircase are finished. On the first floor, the last preparations of interior finishing before the carpenter enters – the floors are ready, we only install Flor-boxes. On the ground floor: tiles in all rooms made, mirrors installed, shelving appeared in the warehouse of small spare parts. We start to take care of cleanliness – washing windows, floors, doors, etc.

Outside: installed weather stations, programmed elevation blinds, poured foundation for the entrance barrier.

Our new purchase was also delivered: a 4-way reach truck, which will move between the cantilever racks in the hall, arranging refurbished high-speed doors for our customers.

We hope that the next post will inform about the investment submission for technical acceptance 😉