Construction progress – 10 Jul.

Inside: internal plasters finished, underfloor heating pipes laid, mechanical ventilation ducts in progress, main electrical switchboard installed, passages through the fire wall secured, we are finishing insulation of the wall between the hall and the brick building, this morning the end flooring team came in.
Outside: the façade is 80% made, the paving stones are finished.