Inside: the floors have been finished; the engine room has started the process of technical equipment, the air handling unit has been installed, the contractor continues to distribute the ducts; the wall between the hall and the brick building was plastered; internal window sills are embedded; the assembly of the joinery has started; electricians have started work on smaller switching stations.
Exterior: façade works completed; the distribution of rainwater drainage is completed.